Solar Panel Installation in Bradford
What a full solar PV installation involves on a Bradford home, from roof survey and system design through to commissioning, grid notification and your MCS certificate.
What the installer is actually designing
A solar installation is a system, not a pile of panels. The installer is balancing four things at once: how much roof you have and which way it faces, how much electricity you use and when, what the inverter can sensibly handle, and what the roof structure will carry. Change one and the others move.
In Bradford that usually starts with the roof. The housing here is mostly stone terraces and back-to-backs, interwar semis, and estates across the outer districts, and the coverings are typically stone slate and Welsh slate on the older stock, concrete tile on later housing. That combination decides the mounting system before anything else is chosen.

The survey
A remote design from aerial imagery is fine for an indicative quote. Before anything is ordered, a good installer will want eyes on the roof: covering and condition, batten and rafter spacing, the state of the flashings, access for scaffolding, the route for cabling, and where the consumer unit sits.
Bradford's stone slate roofs are heavy and the timbers were sized for that load, so a structural check is more than a formality here.
Mounting and fixings
On a pitched tile or slate roof the installer lifts tiles, fixes roof anchors to the rafters, seals the penetration, and runs aluminium rails across the anchors. Panels clamp to the rails. Done properly the roof is weathertight and the fixings are into structure, not into batten.
Slate needs more care than concrete tile — it is thinner, more brittle, and less forgiving of a badly placed anchor. Flat roofs use a ballasted or tilted frame instead, with no penetration at all in most cases.
Electrical work
Panels are wired in strings to the inverter, with DC isolation at the array and AC isolation at the inverter. The AC side lands at the consumer unit on its own protected way. Generation metering and monitoring are set up at commissioning.
Earthing and bonding get checked as part of this. If the consumer unit is old or already full, that work may need doing first, and it should appear on the quotation rather than as a surprise on the day.
Grid notification
Most domestic systems are notified to Northern Powergrid after the event under G98. Larger systems, or connections where the local network is already constrained, need a G99 application and approval before installation. Your installer handles this; ask which route applies to you before you commit to a date.
Handover
At handover you should receive the MCS certificate for the installation, the system design and performance estimate, the electrical certificate, the manufacturer warranties, the monitoring login and an operation and maintenance manual. Without the MCS certificate you will struggle to get an export tariff, so check it has actually arrived.
Common questions
How long does an installation take?
Do I need scaffolding?
Will the roof leak afterwards?
What does the quote cost?